Completion of Bid B3 of Pearl River Delta Water Resources Allocation Project
Source: Date:2022年12月13日

On October 23, with the "Yuehai 35" shield machine coming out of the tunnel safely in the B3 bid, all the tunnels of the Pearl River Delta Water Resources Allocation Project Group constructed by China Railway Tunnel Group were completed. The total mileage of the three shield construction sections is 27.6 kilometers. Bid B3 crosses Shiziyang in December 2021, which is the third time that the company"s construction project crosses Shiziyang.

The Pearl River Delta Water Resources Allocation Project is one of the  major water conservancy projects. It reaches Gongming Reservoir, crosses Foshan, Guangzhou, Dongguan, Shenzhen and other cities, and has the characteristics of a large investment, a long water transmission line and wide water receiving area. The total length is 113.2 kilometers.